Overview as of October, 2024
Continuing masonry.
Started on the parking lot and roadway at the front of the building.
Exterior sidewalks are beginning.
Interior paint and cabinetry are continuing.
Overview as of September, 2024
Steel has been installed in the auditorium for the balcony.
Masonry is continuing in the gym.
Interior block seal is happening in the corridor.
All trades are continuing and on track.
The front parking lot and exterior concrete are beginning.
The new LDS seminary building is currently under construction.
Overview as of August, 2024
Masonry in the auditorium is complete.
The steel decking and masonry in the center commons area is complete.
Masonry in the gym is continuing.
Overview as of July, 2024
The high walls in the auditorium have been topped out.
Structural steel in the commons area is beginning.
Masonry in the gym and auditorium are continuing.
Overview as of June, 2024
Cabinetry is beginning to be installed.
Painting is beginning.
Masonry in the gym and auditorium is continuing.
Overview as of May, 2024
Masonry in the auditorium and gym are beginning.
Roofing is continuing.
The project is moving along well.
Overview as of April, 2024
Masonry is going well and is continuing.
The B wing masonry is complete.
Metal work is beginning in the B wing.
Masonry in the kitchen is complete.
Masonry in the gym is beginning.
Overview as of March, 2024
Masonry is continuing.
The B wing (south area) is almost complete.
Cabinets are currently being installed.
Air handlers have been received.
Metal roof decking is going on and being worked on.
Overview as of February, 2024
Masonry is continuing and will be beginning in the gym and wrestling room.
The cell tower equipment is currently being installed. T-Mobile is the vendor.
Began paining interior classrooms in two areas.
Five air handlers will be received this month.
Overview as of January, 2024
Masonry is continuing. Currently working in areas B, C, & D. (C&D are the gym area.)
Main floor concrete slabs are 100% complete.
Floors on the second floor are 35% complete.
Roof work is beginning.
Trusses and roof decking are being installed in areas A and G with roof membrane to follow.
Areas F and G- the roof membrane is installed.
T-Mobile is installing equipment on the cell tower.
The school is approximately 47% complete.
Overview as of December, 2023
90% of the main floor and 25% of the second floor have been poured.
There is structural fill around the entire building to ensure work is possible throughout the winter months.
Stadium is 100% complete.
The parking lot between the junior high and high school is complete.
The school is approximately 40% complete.