Payson High School Construction

Overview as of October, 2024

  • Continuing masonry.

  • Started on the parking lot and roadway at the front of the building.

  • Exterior sidewalks are beginning.

  • Interior paint and cabinetry are continuing.

Overview as of September, 2024

  • Steel has been installed in the auditorium for the balcony.

  • Masonry is continuing in the gym.

  • Interior block seal is happening in the corridor.

  • All trades are continuing and on track.

  • The front parking lot and exterior concrete are beginning.

  • The new LDS seminary building is currently under construction.

Overview as of August, 2024

  • Masonry in the auditorium is complete.

  • The steel decking and masonry in the center commons area is complete.

  • Masonry in the gym is continuing.

Overview as of July, 2024

  • The high walls in the auditorium have been topped out.

  • Structural steel in the commons area is beginning.

  • Masonry in the gym and auditorium are continuing.

Overview as of June, 2024

  • Cabinetry is beginning to be installed.

  • Painting is beginning.

  • Masonry in the gym and auditorium is continuing.

Overview as of May, 2024

  • Masonry in the auditorium and gym are beginning.

  • Roofing is continuing.

  • The project is moving along well.

Overview as of April, 2024

  • Masonry is going well and is continuing.

  • The B wing masonry is complete.

  • Metal work is beginning in the B wing.

  • Masonry in the kitchen is complete.

  • Masonry in the gym is beginning.

Overview as of March, 2024

  • Masonry is continuing.

  • The B wing (south area) is almost complete.

  • Cabinets are currently being installed.

  • Air handlers have been received.

  • Metal roof decking is going on and being worked on.

Overview as of February, 2024

  • Masonry is continuing and will be beginning in the gym and wrestling room.

  • The cell tower equipment is currently being installed. T-Mobile is the vendor.

  • Began paining interior classrooms in two areas.

  • Five air handlers will be received this month.

Overview as of January, 2024

  • Masonry is continuing. Currently working in areas B, C, & D. (C&D are the gym area.)

  • Main floor concrete slabs are 100% complete.

  • Floors on the second floor are 35% complete.

  • Roof work is beginning.

    • Trusses and roof decking are being installed in areas A and G with roof membrane to follow.

    • Areas F and G- the roof membrane is installed.

  • T-Mobile is installing equipment on the cell tower.

  • The school is approximately 47% complete.

Overview as of December, 2023

  • 90% of the main floor and 25% of the second floor have been poured. 

  • There is structural fill around the entire building to ensure work is possible throughout the winter months.

  • Stadium is 100% complete. 

  • The parking lot between the junior high and high school is complete.

  • The school is approximately 40% complete.