Overview as of October, 2024
The foundation for the field house is underway.
Steel for the field house building is beginning to arrive on site.
The field house roadway and parking has been paved.
Landscaping is ongoing.
Overview as of September, 2024
Footings have been poured for the field house.
The gas line has been installed for the main field house building.
Systems training is continuing.
Landscaping is continuing to progress.
Overview as of August, 2024
Landscaping is progressing.
The greenhouse is being installed.
Demolition of the old building is complete.
The new traffic light on Center Street is functioning.
Overview as of July, 2024
Asbestos abatement has been completed.
Demolition of the old building is continuing.
Excavation and preparation for the bus lane and additional parking is beginning.
The gas line for the new building is soon to be installed.
The bleachers and track in the gym are complete.
Lighting and sound system are almost complete in the auditorium.
Construction for the new greenhouse will begin this month.
Overview as of June, 2024
Demolition of the old Spanish Fork High School began on June 3rd.
Asbestos abatement in the old Spanish Fork High School began in the main building and will be completed in three weeks.
Installing bleachers in the gym.
Installing seating in the auditorium.
Completing the track in the gym.
Glass handrail will be completed after the track is complete.
Full occupancy from the Fire Marshall will happen on June 20th.
Overview as of May, 2024
***JOIN US for an OPEN HOUSE on May 20th from 6:00-8:000 pm for a ribbon cutting and tours of the new Spanish Fork High School.***
Landscaping is continuing with sod and landscaping rock being placed.
One of the gymnasium floors is completely finished.
The other gymnasium floor is currently being painted.
Glass handrails are being installed.
Overview as of April, 2024
The auditorium and stage lighting are being installed.
The gymnasium floors have been installed and are currently being painted.
The glass railing in the gymnasium is beginning.
Kitchen equipment is being installed.
Elevators are installed.
Soelberg wall has been installed.
Landscaping is beginning.
The fence to the north of the school is now complete.
Overview as of March, 2024
The bathroom tile in all the bathrooms have been completed.
The equipment in the kitchen is currently being installed.
Flooring on the first floor is being installed.
Concrete around the site is being installed and comping along; walkways, plaza, etc.
The two elevators are at the beginning phase of installation.
The precast concrete stairs in the following areas are being installed: main stairway, auditorium, commons area, and the gyms.
Overview as of February, 2024
The gyms are painted and equipment is currently being installed.
The subfloor in the gyms are close to being installed.
The lighting and partition in the gyms have been installed.
Interactive monitors and whiteboards are currently being installed in classrooms.
The lockers in the locker rooms are currently being installed.
The floors in the locker rooms are complete.
Plumbing fixtures are beginning to be installed.
Data is being installed throughout the building.
The sound system is being installed.
The block wall between the school and the neighbors will be completed by mid February.
Overview as of January, 2024
The auditorium work platform (dance floor) has been removed.
Currently beginning to build the stage in the auditorium.
Currently working on fireproofing all steel structures.
the gym air handlers have arrived and are beginning installation.
Beginning footings and foundation for the masonry wall between the school and the neighbors.
The gyms are currently being painted.
50% complete
The school is approximately 83% complete.
Overview as of December, 2023
Building is now completely waterproof. All roofs are on.
Currently working on the mechanical piping and ductwork in the gyms.
Auditorium ceiling work is almost complete.
80% of the classroom flooring is installed.
Kitchen is close to completion and ready for equipment.
North parking lot is complete.
The school is approximately 83% complete.