Spanish Fork High School Construction

Overview as of October, 2024

  • The foundation for the field house is underway.

  • Steel for the field house building is beginning to arrive on site.

  • The field house roadway and parking has been paved.

  • Landscaping is ongoing.

Overview as of September, 2024

  • Footings have been poured for the field house.

  • The gas line has been installed for the main field house building.

  • Systems training is continuing.

  • Landscaping is continuing to progress.

Overview as of August, 2024

  • Landscaping is progressing.

  • The greenhouse is being installed.

  • Demolition of the old building is complete.

  • The new traffic light on Center Street is functioning.

Overview as of July, 2024

  • Asbestos abatement has been completed.

  • Demolition of the old building is continuing.

  • Excavation and preparation for the bus lane and additional parking is beginning.

  • The gas line for the new building is soon to be installed.

  • The bleachers and track in the gym are complete.

  • Lighting and sound system are almost complete in the auditorium.

  • Construction for the new greenhouse will begin this month.

Overview as of June, 2024

  • Demolition of the old Spanish Fork High School began on June 3rd.

  • Asbestos abatement in the old Spanish Fork High School began in the main building and will be completed in three weeks.

  • Installing bleachers in the gym.

  • Installing seating in the auditorium.

  • Completing the track in the gym.

  • Glass handrail will be completed after the track is complete.

  • Full occupancy from the Fire Marshall will happen on June 20th.

Overview as of May, 2024

  • ***JOIN US for an OPEN HOUSE on May 20th from 6:00-8:000 pm for a ribbon cutting and tours of the new Spanish Fork High School.***

  • Landscaping is continuing with sod and landscaping rock being placed.

  • One of the gymnasium floors is completely finished.

  • The other gymnasium floor is currently being painted.

  • Glass handrails are being installed.

Overview as of April, 2024

  • The auditorium and stage lighting are being installed.

  • The gymnasium floors have been installed and are currently being painted.

  • The glass railing in the gymnasium is beginning.

  • Kitchen equipment is being installed.

  • Elevators are installed.

  • Soelberg wall has been installed.

  • Landscaping is beginning.

  • The fence to the north of the school is now complete.

Overview as of March, 2024

  • The bathroom tile in all the bathrooms have been completed.

  • The equipment in the kitchen is currently being installed.

  • Flooring on the first floor is being installed.

  • Concrete around the site is being installed and comping along; walkways, plaza, etc.

  • The two elevators are at the beginning phase of installation.

  • The precast concrete stairs in the following areas are being installed: main stairway, auditorium, commons area, and the gyms.

Overview as of February, 2024

  • The gyms are painted and equipment is currently being installed.

  • The subfloor in the gyms are close to being installed.

  • The lighting and partition in the gyms have been installed.

  • Interactive monitors and whiteboards are currently being installed in classrooms.

  • The lockers in the locker rooms are currently being installed.

  • The floors in the locker rooms are complete.

  • Plumbing fixtures are beginning to be installed.

  • Data is being installed throughout the building.

  • The sound system is being installed.

  • The block wall between the school and the neighbors will be completed by mid February.

Overview as of January, 2024

  • The auditorium work platform (dance floor) has been removed.

  • Currently beginning to build the stage in the auditorium.

  • Currently working on fireproofing all steel structures.

  • the gym air handlers have arrived and are beginning installation.

  • Beginning footings and foundation for the masonry wall between the school and the neighbors.

  • The gyms are currently being painted.

    • 50% complete

  • The school is approximately 83% complete.

Overview as of December, 2023

  • Building is now completely waterproof. All roofs are on.

  • Currently working on the mechanical piping and ductwork in the gyms.

  • Auditorium ceiling work is almost complete.

  • 80% of the classroom flooring is installed.

  • Kitchen is close to completion and ready for equipment.

  • North parking lot is complete.

  • The school is approximately 83% complete.