Overview as of October, 2024
- The new Red Devil Drive is paved.
- Masonry is ongoing.
- Site is close to having on grade slabs poured.
- Sod for the ball fields will be installed in early October.
Overview as of September, 2024
- The floor in the auditorium is beginning to be poured.
- Masonry is beginning in the gym.
- Utilities on Red Devil Drive will be tied to 400 South.
- The gas line for the new building is being installed.
Overview as of August, 2024
- Bird Park- baseball and softball fields are progressing.
- Concrete on site is at 80% complete.
- Landscaping and turf are beginning.
- The roundabout on Red Devil Drive is complete.
- The new student parking lot is complete.
Overview as of July, 2024
- All trades, except cabinetry, are working on the new building.
- Dirt is continuing to be moved.
- Pipes are being run.
- The fences at Bird Park are being installed.
- The announcer's booth have been painted.
- Baseball field will be CLOSED until the project is complete.
- The new parking lot and new Red Devil Drive roundabout will be completed by August 10th.
- The roundabout will be under construction on Red Devil Drive throughout the summer. That road will be closed for the majority of the summer.
Overview as of June, 2024
- Fencing is beginning to be installed around the baseball field.
- Site concrete on the softball field is beginning.
- Masonry for the dugout on the softball field is beginning.
- Baseball field will be CLOSED until the project is complete.
- The roundabout on Red Devil Drive will begin on June 10th and will be under construction throughout the summer.
- Red Devil Drive will be closed for the majority of the summer.
- The new parking lot and the new Red Devil Drive roundabout will be completed by August 10th.
- There are two small parking lots that have been paved.
- The school is progressing well.
Overview as of May, 2024
- Grading is complete on the baseball and softball fields.
- Landscaping around the fields is beginning this month.
- Masonry and concrete slabs are continuing on the building site.
- The roundabout will be under construction on Red Devil Drive throughout the summer.
- Red Devil Drive will be closed for the majority of the summer.
- SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
- Fields will remain in use until the season ends and then construction will begin.
- Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
- Baseball field: new dugouts, new backstops, and announcer booth upgrade.
Overview as of April, 2024
- Underground irrigation piping is complete.
- Red Devil Drive is underway.
- Temporary power has been installed for the building.
- Masonry, electrical, and concrete is still progressing.
- The concrete footings for the gymnasium have begun.
- Bird Park construction is beginning.
- SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
- Fields will remain in use until the season ends and then construction will begin.
- Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
- Baseball field: new dugouts, new backstops, and announcer booth upgrade.
- SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
Overview as of March, 2024
- The bidding process for Pack #3 is complete and pending approval from the Board.
- The concrete pad is progressing.
- Irrigation piping through Bird Park is beginning.
- Masonry, concrete and electrical are all continuing.
- Beginning to work with the city on preparing for the roadway on 400 South.
- Bird Park construction will begin pending Board approval on March 13. SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
- Fields will remain in use until the season ends and then construction will begin.
- Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
- Baseball field: new dugouts, new backstops, and announcer booth upgrade.
- ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***
Overview as of February, 2024
- Underground site utilities are continuing to be installed.
- 40% of the concrete slabs have been poured.
- Bird Park plans are out to bid and construction will be expected to begin in early March.
- ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***
Overview as of January, 2024
- Beginning masonry.
- Construction pad is 100% complete.
- Irrigation piping is 75% complete.
- Footings and floors are continuing to be poured.
- Coordination with Springville City on Bird Park plans (Bld Pack #3) are being finalized.
- The school is approximately 17% complete.
Overview as of December, 2023
- Irrigation piping is underway- 30% complete.
- Beginning stages of pouring floors.
- Bid for Bird Park- baseball and softball fields- will be going out in February.
- The school is approximately 10% complete.