Overview as of October, 2024

  • The new Red Devil Drive is paved.
  • Masonry is ongoing.
  • Site is close to having on grade slabs poured.
  • Sod for the ball fields will be installed in early October.

Overview as of September, 2024

  • The floor in the auditorium is beginning to be poured.
  • Masonry is beginning in the gym.
  • Utilities on Red Devil Drive will be tied to 400 South.
  • The gas line for the new building is being installed.

Overview as of August, 2024

  • Bird Park- baseball and softball fields are progressing.
    • Concrete on site is at 80% complete.
    • Landscaping and turf are beginning.
  • The roundabout on Red Devil Drive is complete.
  • The new student parking lot is complete.

Overview as of July, 2024

  • All trades, except cabinetry, are working on the new building.
  • Dirt is continuing to be moved.
  • Pipes are being run.
  • The fences at Bird Park are being installed.
  • The announcer's booth have been painted.
  • Baseball field will be CLOSED until the project is complete.
  • The new parking lot and new Red Devil Drive roundabout will be completed by August 10th.
  • The roundabout will be under construction on Red Devil Drive throughout the summer. That road will be closed for the majority of the summer.

Overview as of June, 2024

  • Fencing is beginning to be installed around the baseball field.
  • Site concrete on the softball field is beginning.
  • Masonry for the dugout on the softball field is beginning. 
  • Baseball field will be CLOSED until the project is complete.
  • The roundabout on Red Devil Drive will begin on June 10th and will be under construction throughout the summer. 
  • Red Devil Drive will be closed for the majority of the summer.
  • The new parking lot and the new Red Devil Drive roundabout will be completed by August 10th.
  • There are two small parking lots that have been paved.
  • The school is progressing well.

Overview as of May, 2024

  • Grading is complete on the baseball and softball fields.
  • Landscaping around the fields is beginning this month.
  • Masonry and concrete slabs are continuing on the building site.
  • The roundabout will be under construction on Red Devil Drive throughout the summer.
  • Red Devil Drive will be closed for the majority of the summer.
  • SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
    • Fields will remain in use until the season ends and then construction will begin.
    • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
    • Baseball field: new dugouts, new backstops, and announcer booth upgrade.

Overview as of April, 2024

  • Underground irrigation piping is complete.
  • Red Devil Drive is underway.
  • Temporary power has been installed for the building.
  • Masonry, electrical, and concrete is still progressing.
  • The concrete footings for the gymnasium have begun.
  • Bird Park construction is beginning.
    • SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
      • Fields will remain in use until the season ends and then construction will begin.
      • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
      • Baseball field: new dugouts, new backstops, and announcer booth upgrade.

Overview as of March, 2024

  • The bidding process for Pack #3 is complete and pending approval from the Board.
  • The concrete pad is progressing.
  • Irrigation piping through Bird Park is beginning.
  • Masonry, concrete and electrical are all continuing.
  • Beginning to work with the city on preparing for the roadway on 400 South.
  • Bird Park construction will begin pending Board approval on March 13. SEE MAP BELOW FOR ALTERNATE ACCESS TO FIELDS.
    • Fields will remain in use until the season ends and then construction will begin.
    • Softball field: new field, new lighting, new backstops, new dugouts, and concession stand upgrade.
    • Baseball field: new dugouts, new backstops, and announcer booth upgrade.
  • ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***

Overview as of February, 2024

  • Underground site utilities are continuing to be installed.
  • 40% of the concrete slabs have been poured.
  • Bird Park plans are out to bid and construction will be expected to begin in early March.
  • ***Red Devil Drive will be closed during Spring Break to install irrigation piping.***

Overview as of January, 2024

  • Beginning masonry.
  • Construction pad is 100% complete.
  • Irrigation piping is 75% complete.
  • Footings and floors are continuing to be poured.
  • Coordination with Springville City on Bird Park plans (Bld Pack #3) are being finalized.
  • The school is approximately 17% complete.

Overview as of December, 2023

  • Irrigation piping is underway- 30% complete.
  • Beginning stages of pouring floors. 
  • Bid for Bird Park- baseball and softball fields- will be going out in February.
  • The school is approximately 10% complete.