Overview as of September, 2024
- Footings have been poured for the field house.
- The gas line has been installed for the main field house building.
- Systems training is continuing.
- Landscaping is continuing to progress.
Overview as of August, 2024
- Landscaping is progressing.
- The greenhouse is being installed.
- Demolition of the old building is complete.
- The new traffic light on Center Street is functioning.
Overview as of July, 2024
- Asbestos abatement has been completed.
- Demolition of the old building is continuing.
- Excavation and preparation for the bus lane and additional parking is beginning.
- The gas line for the new building is soon to be installed.
- The bleachers and track in the gym are complete.
- Lighting and sound system are almost complete in the auditorium.
- Construction for the new greenhouse will begin this month.
Overview as of June, 2024
- Demolition of the old Spanish Fork High School began on June 3rd.
- Asbestos abatement in the old Spanish Fork High School began in the main building and will be completed in three weeks.
- Installing bleachers in the gym.
- Installing seating in the auditorium.
- Completing the track in the gym.
- Glass handrail will be completed after the track is complete.
- Full occupancy from the Fire Marshall will happen on June 20th.
Overview as of May, 2024
- ***JOIN US for an OPEN HOUSE on May 20th from 6:00-8:000 pm for a ribbon cutting and tours of the new Spanish Fork High School.***
- Landscaping is continuing with sod and landscaping rock being placed.
- One of the gymnasium floors is completely finished.
- The other gymnasium floor is currently being painted.
- Glass handrails are being installed.
Overview as of April, 2024
- The auditorium and stage lighting are being installed.
- The gymnasium floors have been installed and are currently being painted.
- The glass railing in the gymnasium is beginning.
- Kitchen equipment is being installed.
- Elevators are installed.
- Soelberg wall has been installed.
- Landscaping is beginning.
- The fence to the north of the school is now complete.
Overview as of March, 2024
- The bathroom tile in all the bathrooms have been completed.
- The equipment in the kitchen is currently being installed.
- Flooring on the first floor is being installed.
- Concrete around the site is being installed and comping along; walkways, plaza, etc.
- The two elevators are at the beginning phase of installation.
- The precast concrete stairs in the following areas are being installed: main stairway, auditorium, commons area, and the gyms.
Overview as of February, 2024
- The gyms are painted and equipment is currently being installed.
- The subfloor in the gyms are close to being installed.
- The lighting and partition in the gyms have been installed.
- Interactive monitors and whiteboards are currently being installed in classrooms.
- The lockers in the locker rooms are currently being installed.
- The floors in the locker rooms are complete.
- Plumbing fixtures are beginning to be installed.
- Data is being installed throughout the building.
- The sound system is being installed.
- The block wall between the school and the neighbors will be completed by mid February.
Overview as of January, 2024
- The auditorium work platform (dance floor) has been removed.
- Currently beginning to build the stage in the auditorium.
- Currently working on fireproofing all steel structures.
- the gym air handlers have arrived and are beginning installation.
- Beginning footings and foundation for the masonry wall between the school and the neighbors.
- The gyms are currently being painted.
- The school is approximately 83% complete.
Overview as of December, 2023
- Building is now completely waterproof. All roofs are on.
- Currently working on the mechanical piping and ductwork in the gyms.
- Auditorium ceiling work is almost complete.
- 80% of the classroom flooring is installed.
- Kitchen is close to completion and ready for equipment.
- North parking lot is complete.
- The school is approximately 83% complete.