Overview as of April, 2024
- The auditorium and stage lighting are being installed.
- The gymnasium floors have been installed and are currently being painted.
- The glass railing in the gymnasium is beginning.
- The track surfacing will begin next week.
- Kitchen equipment is being installed.
- Elevators are installed.
- Soelberg wall has been installed.
- Landscaping is beginning.
- The fence to the north of the school is now complete.
Overview as of March, 2024
- The bathroom tile in all the bathrooms have been completed.
- The equipment in the kitchen is currently being installed.
- Flooring on the first floor is being installed.
- Concrete around the site is being installed and comping along; walkways, plaza, etc.
- The two elevators are at the beginning phase of installation.
- The precast concrete stairs in the following areas are being installed: main stairway, auditorium, commons area, and the gyms.
Overview as of February, 2024
- The gyms are painted and equipment is currently being installed.
- The subfloor in the gyms are close to being installed.
- The lighting and partition in the gyms have been installed.
- Interactive monitors and whiteboards are currently being installed in classrooms.
- The lockers in the locker rooms are currently being installed.
- The floors in the locker rooms are complete.
- Plumbing fixtures are beginning to be installed.
- Data is being installed throughout the building.
- The sound system is being installed.
- The block wall between the school and the neighbors will be completed by mid February.
Overview as of January, 2024
- The auditorium work platform (dance floor) has been removed.
- Currently beginning to build the stage in the auditorium.
- Currently working on fireproofing all steel structures.
- the gym air handlers have arrived and are beginning installation.
- Beginning footings and foundation for the masonry wall between the school and the neighbors.
- The gyms are currently being painted.
- The school is approximately 83% complete.
Overview as of December, 2023
- Building is now completely waterproof. All roofs are on.
- Currently working on the mechanical piping and ductwork in the gyms.
- Auditorium ceiling work is almost complete.
- 80% of the classroom flooring is installed.
- Kitchen is close to completion and ready for equipment.
- North parking lot is complete.
- The school is approximately 83% complete.